During the second week of July, the connection of wells 2H and 3H to the Atlanta FPSO, operating in the field of the same name, was completed.
The wells are currently undergoing testing and stabilization. Both wells have previously produced through the advance production system (FPSO Petrojarl I). The Atlanta project is still in the production and automation systems testing phase, and fluctuations in daily production are expected during this period.
With the completion of the connection, the Atlanta Field now has six wells connected to the FPSO Atlanta.
BRAVA expects to reach peak production and operational efficiency for the asset over the coming months.